TM 55-8145-202-14
4-30. GENERATION SET, DIESEL - Continued
b. Installation.
(1) Attach lifting device rated for 1 ton to the generator set lifting eyes and lift generator set onto the
container.
(2) Install rear mounting hardware consisting of two capscrews (7), lockwashers (8), plates (5) to secure the
(3) Install to capscrews (3), lockwashers (4) and plates (5) to secure the front of the generator set to
container.
(5) Remove cap from fitting and plug from fuel line. Connect auxiliary fuel line (2).
(6) Connect power cable (1).
Section VII. PREPARATION FOR STORAGE OR SHIPMENT
4-31.
SECURITY PROCEDURES.
Refer to AR 190-11 or AR 190-13.
4-32.
ADMINISTRATIVE STORAGE
a.
Placement of equipment in administrative storage should be for short periods of time when a shortage of
maintenance effort exists. Item should be mission ready within 24 hours or within the time factors as
determined by the directing authority. During the storage period, appropriate maintenance records will be
kept.
b.
Before placing equipment in administrative storage, current maintenance services and equipment
serviceable criteria (ECS) evaluation should be completed, shortcomings and deficiencies should be
corrected, and all modification work orders (MWOs) should be applied.
c.
Remove all cargo, containers, and packaging materials from refrigerated container.
d.
Wash container interior with fresh, clean water and detergent. Rinse with clean water and allow container
interior to dry before closing rear doors.
e.
If container was used in a salt air environment, wash container exterior with detergent and fresh water.
Rinse with clean water and allow to dry.
f.
Storage Site Selection. Inside storage is preferred for items selected for administrative storage. If inside
storage is not available keep container away from corrosive materials, such as saltwater spray.
Special instructions for administrative storage.
Placement of equipment in administrative storage should be for short periods of time when a shortage of
mainetenance efforts exists. Items should be in mission readiness within 24 hours of within the time factors
as determined by the directing authority. During the storage period, appropriate maintenance records will be
kept.
Before placing the equipment in administrative storage, current preventive maintenance checks and
services should be completed, shortcomings and deficiencies should be corrected, and all Modifications
Work Order (MWO) should be applied.
Storage site selection. Inside storage is preferred for items selected for administrative storage. If Inside
storage is not available , trucks, vans, conex container, and other containers may be used.
4-54