TM 10-3930-675-24-2
BOOM FOLDING CONTROL VALVE REPLACEMENT - CONTINUED
0172 00
REMOVAL
1.
Disconnect nine hoses (2) from fittings at control valve (8).
2.
Remove four nuts (5), screws (6), washers (7), and control valve (8) from remote hydraulic control compartment.
NOTE
Perform step 3 to remove fittings from control valve, if a new control valve is being installed.
3.
Remove tee (3), adapter fittings (1), and nipples (4) from control valve (8).
2
2
1
3,4
5,6,7
350-885
1
8
INSTALLATION
NOTE
Refer to General Maintenance Instructions (WP 0284 00) for complete instructions on connecting
hydraulic hoses and applying proper torque.
Perform step 1 to install fittings removed from old control valve, if a new control valve is being
installed.
1.
Install nipples (4), adapter fittings (1), and tee (3) on control valve (8).
2.
Install control valve (8) in remote hydraulic control compartment with four washers (7), screws (6), and nuts (5).
3.
Connect nine hoses (2) to fittings at control valve (8).
4.
5.
Start engine (TM 10-3930-675-10), operate control valve levers, and check for leaks.
6.
Install new tiedown straps as necessary to support hydraulic hoses.
NOTE
Replace hydraulic reservoir return filters after 100 hours of operation (WP 0185 00).
END OF WORK PACKAGE
0172 00-2