TM 10-3930-641-34-2
ARTICULTED HITCH DISASSEMBLY/ASSEMBLY (CONT)
(Sheet 10 of 16)
LOCATION/ITEM
ACTION
REMARKS
7.
Upper bearing cup (21)
Lower temperature to -900 to -110F
(-32 to -430C) and install in bore.
8.
Bearing driver
Use to make bearing cup contact bearing cone.
9.
Shims (25)
Install original amount.
10.
Upper cap (19)
Install.
11. Six capscrews (16)
Install an equal distance apart and tighten
evenly.
12.
Stud, nut and adapter
Connect to bearing cones as shown. Use a
torque wrench to check amount of torque
needed to turn bearing cones.
NOTE
The amount of torque must not be less than
80 lb. in. (9 N-m) or more than 400 lb. in.
(45 N-m). Remove or install shims (25) until
you have the correct amount of torque.
Go on to Sheet 11
6-45