TM 10-3930-675-20-2
0148 00-6
BOOM-TO-BOOM EXTENSION FLEXIBLE CONVEYER MAINTENANCE - CONTINUED
0148 00
ASSEMBLY
NOTE
Perform following steps to install links to conveyer and assemble conveyer.
1.
Ensure crossbar (25) of link (26) to be assembled and crossbar of link (28) of conveyer are removed at each connection
point.
2.
Position link (26) to conveyer at a slight angle and install one side of link to conveyer by pressing inward on side of link.
3.
Install other side of link (26) to conveyer by pressing inward on side of link.
4.
Repeat steps 1 thru 3, as necessary, to install links to conveyer and to assemble two sections of conveyer.
5.
Position each of two clips (29) to each link (28) of conveyer at an angle and press down firmly to install.
6.
Position crossbar (25) to links (26) and two spacers (27) at an angle and press down firmly to install.
7.
Repeat steps 5 and 6 at top and bottom of links that were installed.
26
28
29
29
28
26
25
26
27
26